Monday, 22nd September 2024 - first flooding
Tuesday, 23rd September 2024 - reopening
Friday 27th September 2024 - 2nd flooding
Saturday, 28th September 2024 & Sunday, 29th September 2024
Roads were cleared and there was some relief from the rainy weather with a sunny, calm weekend. However, more rain was forecast to start late on Sunday, emergency services prepared more sandbags for the locals to help themselves to. More barriers were created at WCC and stayed in place for the coming week. Luckily, there was no more flooding for the time being.
Rugs and Doormats have been professionally cleaned and treated immediately following the flooding. We would like to thank Vista Carpet Cleaning for their professional and quick help with this.
A dehumidifier has been operational for two weeks to dry out the Lobby.
October 2024
Next to minor damage to skirting boards, doors, seals etc, we have identified significant damage to the Main Hall parquet floor after the second flood, with warping reaching up to almost a foot high, cracking and bricks popping out, making it unsalvageable.
November 2024
Removal of the Main Hall flooring began on October 30th and has now been completed. We would like to extend our sincere thanks to Mr. Osborne of Osborne Woodcare Ltd for his excellent work and expertise during this process.
Affected areas continue to dry out as part of the recovery process.
December 2024
7.12. - A survey was conducted in early November, and we are currently awaiting the report, lab results, and feedback from our insurance provider. Progress on this front unfortunately has been slower than anticipated.
In the meantime, we have proactively met with several companies and contractors to gather quotes for potential repairs and works. This will allow us to move forward swiftly once we receive confirmation from the insurance.
Additionally, we are exploring options for future flood-proofing measures for the premises. Given the circumstances, we recognise that this may not be an isolated event and are taking steps to mitigate similar risks in the future.
20.12. - We have received the green light to proceed with works in the kitchen and storage room flooring. The removal of units and appliances in both areas, as well as the uplifting and disposal of the old flooring, has now been completed.
A huge thank you to JST Home Improvements for their fantastic work.
Now that the old flooring has been removed, these areas can continue to dry out more effectively in preparation for the installation of new flooring in the new year.
January 2025
We are making progress with booking in dates for outstanding works to take place during February.
February 2025
Most of the outstanding major works are taking place this month - we are a big step closer to reopening!
4.2. - New flooring has been fitted in the Main Hall kitchen, and storage room. Big thanks to Roysia Flooring LTD for their work!
10.2. - The kitchen units and appliances are back in place, and some of the finishing touches have been completed, including touching up the storage room walls, applying new sealant around the Lobby edges, and installing a new heavy-duty storage shelf.
Ongoing - Work on the main hall flooring is currently underway. This is a major project requiring several preparation sessions spread over multiple days before the new flooring can be installed.
WCC was mentioned in BBC online articles on 2nd October and 15th November
Our Chair of Trustees gave a live interview on BBC Four Counties Radio on 3rd October